How to price a roofing job: a re-roof worked through end to end

How to price a re-roof: the survey, scaffold, strip, membrane, battens, tiles, leadwork, rain days and disposal, with one roofing quote worked out in full.

Part of the Pricing series · How to price a job and not lose money

A re-roof is priced the same way as any job: work out the days for each stage, cost your labour, your labourer, the materials and the scaffold, add the costs people forget, recover your overheads for the days the job takes, then put your markup on top. What makes roofing different is the weather and what you cannot see until the tiles are off, so decide who carries the rain days before you send the price, and put the hidden timber on the quote as an allowance rather than a guess.

This page sits under our guide to pricing a job. It walks one strip and re-cover of a pitched tiled roof through from the survey to the figure on the quote; our guide to pricing an extension does the same for a bigger build. The other worked examples are a bathroom refit, a kitchen fit, a rewire, a decorating job and a patio. The numbers are an illustration built from one set of costs, not a market rate: use your own.

Part 1Start at the survey


Most of the money lost on a re-roof is lost by pricing from the ground.

  • Get into the loft. Look at the rafters, the old felt, any daylight or staining. Wet or sagging timber is the part of the job that moves.
  • Measure the roof, not the house. Hips, valleys, verges and the ridge each take their own time and materials.
  • Look at the chimney and every abutment. Leadwork is where a lot of the days go.
  • Check what the new covering weighs. A heavier tile than the old one puts more load on the rafters. Raise it with building control or an engineer before you price.
  • Look at where the scaffold and the skip will stand.
  • Ask when the house was built or last re-roofed. HSE says asbestos can be present in any building built or refurbished before 2000, and its list for the outside of a house includes roofing felt, cement slates, soffits and gutters. If you suspect it, have it tested before you price the strip.

Anything you genuinely cannot see goes on the quote as a provisional sum, not as a guess folded into the price.

Part 2Check the rules before you price


Building regulations. In England, re-roofing can be building work under the building regulations. Renovating a large part of a roof can bring in energy efficiency requirements, which can mean insulation you had not priced, so ask building control before you strip. A roofer registered with a competent person scheme for replacing roof coverings can self-certify the work instead of going through building control. Wales, Scotland and Northern Ireland set their own building rules, so check with building control there.

Bats. In England, bats and their roosts are protected by law, and the government's guidance lists repairing or replacing a roof among the work that can affect them. It is an offence to damage or destroy a roost, or to intentionally or recklessly disturb a bat sheltering in one. If there is any sign of bats, a bat survey comes before the strip, and work that cannot avoid harming bats or a roost needs a licence from Natural England. That can move your start date, so say so on the quote. Scotland, Wales and Northern Ireland have their own guidance.

Scaffold on the pavement. In England and Wales, scaffold that obstructs a public highway, pavement included, needs a licence from the highway authority, usually the council. Ask the scaffolder whether their price includes it.

Part 3Break it into stages and days


The example below is a semi-detached house with a gable roof and one chimney, done by you and a labourer, in these stages:

  • Strip: tiles, battens and old felt off and into the skip.
  • Timber repairs: whatever the strip uncovers.
  • Membrane and battens: set out for the new tile.
  • Tiling: the slopes covered.
  • Ridge, verges and eaves: finished and fixed.
  • Leadwork and gutters: chimney flashings, abutments, new gutters and downpipes.

That comes to 8 working days, with the scaffold up before you start. Strip only what you can make weathertight the same day.

Part 4The weather, and who carries the risk


Rain days are roofing's own risk, and the quote is where you decide whose risk it is. You can carry it yourself: put a weather allowance in the price, in days, and quote a figure that does not change if it rains. The example below allows 1 day.

Or you can share it: price the working days only, and say on the quote that days lost to weather extend the programme, and whether that changes the price. A customer who thinks the price is fixed and a roofer who thinks rain days are extra will both be sure they are right.

Part 5Materials and the scaffold


List materials by what you will actually buy, with enough over for cuts and breakages. If old tiles are being reused, say so on the quote: one that breaks on the day is a new tile you buy. If the customer has not chosen the tile, put a PC sum in for it.

The scaffold is normally a subcontracted line. Get the scaffolder's price in writing, with the hire period and the cost of each extra week, because rain that stretches the job stretches the hire too.

Part 6The costs people forget


The hidden costs of a job on a re-roof are mostly about getting things up and down: skips for the old roof, often more than one; the merchant's charge for loading the roof; sheeting for the nights it is open; the blades and nails a whole roof goes through. Each is its own line, costed like the work, so your markup applies to the full cost.

Part 7The worked example


Here is the job above priced in full. Your labour is costed at the wage you pay yourself, £250 a day, and your labourer at £160 a day as a separate line; your overheads are recovered separately, at £55 for each day the job takes (our guide to working out your day rate shows where both figures come from); and the markup is 20% of the bare cost. The overhead covers 9 days: the 8 working days plus the weather day.

A re-roof of a semi-detached house, 8 working days plus 1 weather day
Your labour, 8 days at £250£2,000.00
Labourer, 8 days at £160£1,280.00
Weather allowance, 1 day for you and the labourer£410.00
Scaffold, erected, hired and struck, subcontracted£1,400.00
Tiles, ridge and dry-fix systems£2,350.00
Membrane, battens, nails and clips£620.00
Leadwork: chimney flashings and abutments£380.00
Gutters and downpipes, renewed£360.00
Skips and disposal of the old roof£640.00
Merchant delivery and roof loading£120.00
Temporary sheeting for overnight cover£90.00
Consumables: blades, fixings, sealant£75.00
Provisional sum: rafter and fascia repairs, if the strip finds them£300.00
Bare cost of the job£10,025.00
Overhead recovery, 9 days at £55£495.00
Markup at 20% of the bare cost£2,005.00
Price before VAT£12,525.00

Two things about how that reaches the customer. The overhead is never a line on the quote: it is spread through the line prices, so the customer sees the work, not your van insurance. And the markup is a markup on cost, not a margin: £2,005 on a £12,525 price is a margin of about 16%. Our guide to markup vs margin explains why the difference matters.

If you are VAT registered, VAT goes on top, and a quote to a homeowner shows the total including it: here £12,525 plus £2,505 VAT at 20%, or £15,030.

Part 8Put it on a quote that holds


The timber allowance is inside that figure, marked up like every other line, and labelled on the quote as a provisional sum to be confirmed once the roof is stripped. Anything the strip finds beyond it is a variation: price it and get it agreed before you do the work, with the roof made safe in the meantime.

A re-roof suits a deposit that covers the scaffold and the tiles, and a balance on completion; on a bigger roof, add a stage payment when the membrane and battens are on. Then write in the weather terms, the start-date conditions and the exclusions, such as a chimney rebuild. Our guide on what to put in a quote covers the rest.

Common questionsPricing a roofing job: quick FAQ


How do I price a re-roof?

Survey it from the loft as well as the ground, put days against each stage, and cost your labour, your labourer, the scaffold and the materials. Add skips, sheeting and a weather allowance, recover your overheads for the days, and add your markup to the bare cost.

Who pays if rain stops the job?

Whoever the quote says. Put a weather allowance in a fixed price and carry the risk yourself, or say on the quote that the programme moves with the weather and whether the price does.

Do I need building regulations approval to re-roof?

In England it can be, and renovating a large part of a roof can bring in energy efficiency requirements. A roofer in a competent person scheme for roof coverings can self-certify instead. The rules differ elsewhere in the UK, so ask building control before you strip.

Should the scaffold go on my quote?

If you are arranging it, yes, as its own line priced from the scaffolder's written quote, with your markup on it. Say what hire period it covers and what happens if the job overruns.

Price it once, properly

TradeDraft prices the job the way this page does: your labour, your labourer, materials and subcontractors as lines, your overheads recovered for the days the job takes and spread through the prices, and your markup on the bare cost, with the margin shown before you send. A line you mark as provisional is flagged on the quote as an allowance to be confirmed. Free for 30 days, no card needed. After that it's £45/month or £450/year, cancel anytime. Start by 5 April 2027 and it’s £22.50/month for your first 12 months. See TradeDraft's quoting software for roofers.

Price a job free

Want to keep this? Get our four core guides (VAT & CIS, Pricing a Job, Getting Paid, CIS for Subcontractors) as print-ready PDFs, plus a one-page job-pricing checklist — free.

We use your email to send you the toolkit, and to send updates only if you tick the box. See our Privacy Policy.

This guide is general information for UK tradespeople, current to the best of our knowledge in 2026, and is not tax, accounting or legal advice. Rates, thresholds and how they apply to you change, so confirm your position with HMRC, a qualified accountant or a solicitor before relying on it. TradeDraft accepts no liability for decisions made on the basis of this guide. Questions: hello@tradedraft.co.uk.