How to price a kitchen fit, from the survey to the figure on the quote

How to price a kitchen fit: the survey, stages and days, worktops, the gas and electrics, the costs people forget, overhead and markup, worked in full.

Part of the Pricing series · How to price a job and not lose money

To price a kitchen fit, work out the days for each stage from strip-out to making good, cost your labour and materials, add the electrician, the gas engineer and the worktop company as subcontract lines, add the costs people forget, recover your overheads for the days on site, then put your markup on the bare cost. Kitchens go wrong in two places: the services behind the old units, and the worktops, often made and fitted by someone else on a date you do not control. Price both openly.

This page sits under our guide to pricing a job. It walks one kitchen fit from the survey to the price; our guide to pricing a bathroom does the same for a smaller room. The other worked examples are a extension, a rewire, a re-roof, a decorating job and a patio. The figures are an illustration built from one set of costs, not a market rate: use your own.

Part 1What to check before you price


Most of what changes the price of a kitchen is behind the units you are taking out.

  • Who is supplying what. Units, appliances, worktops, sink and tap. On a fit-only kitchen the customer buys the units, which changes your materials line and your risk.
  • The plan against the room. Measure it yourself. Walls out of square and floors out of level cost time on every base unit.
  • Where the services go. If the sink, the hob or the washing machine moves, the pipework and waste move with them. Note the gas supply, the stopcock, and whether the waste can fall from the new sink position to the drain.
  • The electrics. An induction hob or a double oven often needs its own circuit. Look at the consumer unit before you price, not after.
  • The walls, the floor and the access. Tiles to come off and the plaster behind them, a floor going in before the units or after, a narrow hall, room for a skip.

If the layout change takes out a wall, check with building control before you price it. Anything you genuinely cannot see goes on the quote as a provisional sum, not as a guess folded into the price.

Part 2Break it into stages and days


Put a time against each stage you will actually work through. For the fit-only kitchen below, with one person fitting:

  • Strip-out and disposal, with a labourer for the day.
  • First fix: pipework and waste moved, the electrician's first fix.
  • Carcasses: units set out, levelled and fixed, ready for templating.
  • Doors, drawers and panels: fronts, end panels, plinths, cornice.
  • The return visit: sink, tap and appliances connected once the tops are in.
  • Splashback tiling.
  • Second fix and making good: sealant, snagging, adjustments.

That comes to 8 days on site. Stone worktops are templated once the base units are fixed and fitted afterwards, often a week or two on, so the job splits in two. Price the day you come back as a full day of your labour and your overhead, because it is one.

Part 3Materials, worktops and who carries the risk


List materials by what you will actually buy: plumbing fittings and waste, isolating valves, fixings, the splashback tiles and adhesive. If the customer is still choosing the tiles, put in a PC sum.

If the customer supplies the units, say on the quote that you fit what is supplied, so a damaged door or a missing panel, and the return visit it causes, is agreed as extra in advance.

Worktops are the classic risk point. Laminate you cut, joint and fit yourself, so its time is yours to price. Stone and quartz are usually templated, made and fitted by the worktop company, and who that company works for decides who carries the risk. If you buy the tops and they fit under you, a wrong template or a cracked slab is yours to sort, and the price should carry it. If the customer contracts the worktop company directly, write on the quote that your units will be level and fixed ready for templating, and what you will and will not do once the tops arrive.

The gas and electrics are trades of their own. Capping off the old gas supply, moving it, or connecting a gas hob is gas work, and anywhere in the UK, anyone doing gas work as a business must by law be on the Gas Safe Register. Price the engineer as a named subcontract line, or say on the quote that the customer is arranging one.

In England, kitchen electrics are notifiable under Part P of the Building Regulations when the work includes a new circuit (a dedicated supply for an oven or hob is the usual case) or a replacement consumer unit. A kitchen is not a special location in England, so adding a socket to an existing kitchen circuit is not notifiable, though it still has to meet the regulations. In Wales the rule is wider: adding to or altering an existing circuit in a kitchen is notifiable as well. In both, an electrician registered with a competent person scheme can self-certify the work; otherwise the usual route is to tell building control before work starts. Scotland and Northern Ireland have their own systems, so check with the local council there. The certificate is the electrician's, and their quote line should say what it covers.

Part 4The costs people forget


The hidden costs of a job on a kitchen are mostly mess and movement: the skip, protecting floors that are staying, dust screens, the extra merchant run, the blades and sealant. Each is its own line, costed like the work, so your markup applies to the full cost.

Part 5The worked example


Here is the job above priced in full. Labour is costed at the wage you pay yourself, £250 a day; a labourer helps on two days at £150 a day including employer costs; your overheads are recovered separately, at £55 for each day on site (our guide to working out your day rate shows where both figures come from); and the markup is 20% of the bare cost. The customer supplies the units and appliances; you buy the quartz tops and subcontract their templating and fitting.

A fit-only kitchen with quartz worktops, 8 days on site
Your labour, 8 days at £250£2,000.00
Labourer for strip-out and carrying in, 2 days at £150£300.00
Plumbing fittings, waste and isolating valves£160.00
Splashback tiles, adhesive and grout£240.00
Quartz worktops, templated and fitted by the worktop company, subcontracted£2,400.00
Electrician: new oven circuit, sockets moved, certificate, subcontracted£520.00
Gas Safe engineer: supply capped, moved and hob connected, subcontracted£180.00
Skip and disposal£300.00
Floor protection and dust screens£45.00
Consumables: sealant, fixings, blades£75.00
Merchant runs and delivery charges£60.00
Bare cost of the job£6,280.00
Overhead recovery, 8 days at £55£440.00
Markup at 20% of the bare cost£1,256.00
Price before VAT£7,976.00

Two things about how that reaches the customer. The overhead is never a line on the quote: it is spread through the line prices, so the customer sees the work, not your van insurance. And the markup is a markup on cost, not a margin: £1,256 on a £7,976 price is a margin of about 16%. Our guide to markup vs margin explains why the difference matters.

If you are VAT registered, VAT goes on top, and a quote to a homeowner shows the total including it: here £7,976 plus £1,595.20 VAT at 20%, or £9,571.20.

Part 6Put it on a quote that holds


Say plainly what is in the quote and what is not: customer-supplied units, who arranges the worktops, flooring, decoration. A kitchen suits stage payments: a deposit on acceptance, a stage once the units are fixed and the tops templated, and the balance on completion. When the customer adds a larder unit halfway through, price it as a variation before you fit it.

Common questionsPricing a kitchen fit: quick FAQ


How do I price a kitchen fit?

Survey it, break it into stages with days against each, cost your labour and materials, add the electrician, gas engineer and worktop company as subcontract lines, add the skip and the other forgotten costs, recover your overheads for the days on site, then add your markup to the bare cost.

How much should I charge to fit a kitchen?

Whatever your own costs and days add up to, with overhead recovery and markup on top. A price per unit is a fair check against your past jobs, but two kitchens with the same number of units can differ by days once the services move.

How long does it take to fit a kitchen?

It depends on the size, the services and the worktops. The example above is 8 days for one person, including a return day after the stone tops go in. Price your own days, from your own pace.

Who is responsible if a stone worktop does not fit?

Whoever the worktop company works for. If you buy the tops and subcontract the fitting, it is yours to sort. If the customer contracts them directly, say on the quote that the tops are outside your price.

Do I need to be Gas Safe registered to fit a kitchen?

Not to fit units. Anyone doing the gas work as a business, such as capping off, moving the supply or connecting a gas hob, must be on the Gas Safe Register. If that is not you, price a registered engineer as a subcontract line or say the customer is arranging one.

Price it once, properly

TradeDraft prices the job the way this page does: your labour, materials and subcontractors as lines, your overheads recovered for the days the job takes and spread through the prices, and your markup on the bare cost, with the margin shown before you send. Free for 30 days, no card needed. After that it's £45/month or £450/year, cancel anytime. Start by 5 April 2027 and it’s £22.50/month for your first 12 months. See TradeDraft's quoting software for kitchen fitters and for plumbers.

Price a job free

Want to keep this? Get our four core guides (VAT & CIS, Pricing a Job, Getting Paid, CIS for Subcontractors) as print-ready PDFs, plus a one-page job-pricing checklist — free.

We use your email to send you the toolkit, and to send updates only if you tick the box. See our Privacy Policy.

This guide is general information for UK tradespeople, current to the best of our knowledge in 2026, and is not tax, accounting or legal advice. Rates, thresholds and how they apply to you change, so confirm your position with HMRC, a qualified accountant or a solicitor before relying on it. TradeDraft accepts no liability for decisions made on the basis of this guide. Questions: hello@tradedraft.co.uk.