How to price a patio: levels, muck away, slabs and plant, worked through

How to price a patio quote: survey the levels and falls, dig out and muck away, sub-base, slabs, plant hire, overhead and markup, on one 30m² job.

Part of the Pricing series · How to price a job and not lose money

A patio is priced the same way as any job: work out the days for each stage, cost your labour and your labourer's, list the materials, plant and muck away as lines, recover your overheads for the days on site, then put your markup on the bare cost. Most of a patio's cost is under the slabs: get the levels, the digging and the disposal right at the survey and the paving itself is the easy part to price.

This page sits under our guide to pricing a job. It walks one rear-garden patio of about 30 square metres from the survey to the figure on the quote; the guides to pricing a bathroom and pricing an extension do the same for other work. The other worked examples are a kitchen fit, a rewire, a re-roof and a decorating job. The figures are an illustration built from one set of costs, not a market rate: use your own.

Part 1What to check before you price


A patio that loses money usually lost it on the first visit, by guessing.

  • The levels and the falls. Water has to run away from the house, so the patio needs a steady fall in that direction; check the fall the slab supplier recommends. The levels tell you how much comes out, and whether one end needs building up.
  • The damp-proof course. The usual working rule is to keep the finished paving at least 150mm below it. If the lawn is already close to the DPC, you are digging deeper than you thought, and that is more muck and more days.
  • Where the water goes. Off the patio and into a lawn or border, into a channel drain along the house, or into a soakaway. Each is a different price.
  • Access. Measure the side gate. Can a mini digger get through? Is there room on the drive for the grab lorry and a load of sub-base? Muck barrowed through a terraced house is a different job.
  • What is under the lawn. Old foundations, roots, a drain run or a service pipe. Anything you genuinely cannot see goes on the quote as a provisional sum.
  • Who chooses the slabs. If the customer has not picked them yet, put a PC sum in rather than a figure you will argue about later.

Part 2Planning, briefly, and only for England


In England, a hard surface in the garden of a house, such as a patio at or near ground level at the back, is generally permitted development, so it does not need planning permission. The front is different. Where paving, new or replaced, between the front of the house and the road covers more than 5 square metres, it has to be porous, or the water has to run to a lawn, border or other permeable area within the garden; otherwise it needs planning permission.

Permitted development rights can be removed, by an Article 4 direction across an area or by a condition on an earlier planning permission for the house, so if there is any doubt the customer checks with the local planning authority before you start. Wales, Scotland and Northern Ireland set their own rules.

Part 3Break it into stages and days


Write the job in the order you will build it, and put a time against each stage. For the example below, a two-person team:

  • Set-out and levels: pegs, string lines, the falls marked.
  • Dig out and muck away: turf and topsoil off to formation level, loaded straight into the grab lorry where access allows.
  • Edging and sub-base: edging set, membrane down, sub-base compacted in layers.
  • Laying: slabs on a full mortar bed, to the falls, cut in at the edges.
  • Pointing and drainage: joints pointed, the channel drain set, the area cleaned down.

On the example job that comes to 5 days on site. Two people for five days is ten days of wages but five days of overhead, because overhead follows the time on site, not the head count. Be honest about the days. A patio priced at four days that runs to six, because the second grab lorry did not turn up, has given the difference away.

Part 4Materials, plant and who carries the risk


List materials by what you will actually buy: slabs with an allowance for cuts and breakages, sub-base, sharp sand and cement for the bed and the pointing, edging, the channel drain and its fittings, membrane.

Plant hire is a cost like any other, so it gets its own lines: the mini digger for the days you need it, delivery and collection included, and the whacker plate. If you own the plant, charge what you would pay to hire it: it still wears out.

If the customer supplies the slabs, say so on the quote, and say that you lay what is supplied. A short delivery or a batch that does not match costs you time, and the quote is where it is agreed that this is extra.

Your labourer is a line of their own, at what each day costs you. If they are employed, that is their wage plus your employer costs; if they are self-employed, it is what they charge you. Our guide to subcontractor or employee covers which is which.

Part 5The costs people forget


The hidden costs of a job on a patio are mostly about getting things in and getting soil out: the extra grab lorry because the muck bulked up, ground protection on the drive, blades for the saw, fuel, the second trip to the merchant. Each is its own line, costed like the work, so your markup applies to the full cost and not to a cost with holes in it.

Part 6The worked example


Here is the job above priced in full. Your own labour is costed at the wage you pay yourself, £250 a day, and your labourer at £160 a day; your overheads are recovered separately, at £55 for each day on site (our guide to working out your day rate shows where both figures come from); and the markup is 20% of the bare cost.

A rear-garden patio of about 30 square metres, 5 days on site
Your labour, 5 days at £250£1,250.00
Labourer, 5 days at £160£800.00
Slabs for 30 square metres, with an allowance for cuts£1,450.00
Sub-base, sharp sand, cement and membrane£620.00
Edging, channel drain and fittings£340.00
Mini digger hire, 2 days, delivered and collected£360.00
Whacker plate hire£75.00
Muck away, 2 grab lorry loads£560.00
Consumables: cutting blades, pegs, string lines£120.00
Fuel and travel, 5 days at £12£60.00
Bare cost of the job£5,635.00
Overhead recovery, 5 days at £55£275.00
Markup at 20% of the bare cost£1,127.00
Price before VAT£7,037.00

Two things about how that reaches the customer. The overhead is never a line on the quote: it is spread through the line prices, so the customer sees the work, not your van insurance. And the markup is a markup on cost, not a margin: £1,127 on a £7,037 price is a margin of about 16%. Our guide to markup vs margin explains why the difference matters.

If you are VAT registered, VAT goes on top, and a quote to a homeowner shows the total including it: here £7,037 plus £1,407.40 VAT at 20%, or £8,444.40.

Part 7Put it on a quote that holds


Say on the quote what level the patio finishes at, which way it falls, and where the water goes. Those are the three things a customer asks about the first time it rains. Put anything under the ground you could not see, such as soft spots that need digging out deeper, as a provisional sum with how it will be charged. List what is excluded, such as making good the lawn, walls and lighting.

A patio is short enough that two payments often do: a deposit on acceptance that covers the slabs and the plant, and the balance on completion. On a bigger garden job, add a stage when the sub-base is down. Our guide to stage payments covers setting them.

Common questionsPricing a patio: quick FAQ


How do I price a patio?

Survey the levels, falls, access and drainage first. Break the job into stages and put days against each, cost your labour, your labourer, materials, plant hire and muck away as lines, add the costs that are easy to forget, recover your overheads for the days on site, then add your markup to the bare cost.

How far below the damp-proof course should a patio be?

The usual working rule is at least 150mm below the DPC, with the patio falling away from the house. It decides how deep you dig, so check it at the survey.

Do I need planning permission for a patio?

In England, a patio at or near ground level in the back garden generally does not. Paving more than 5 square metres at the front must be porous or drain to a permeable area, or it needs permission. If in doubt, the customer checks with the local planning authority.

What markup should I put on a patio?

That is your call, but put it on the full bare cost, including plant hire and muck away, not just the labour. 20% is a common starting point; a 20% markup on cost is about a 16.7% margin on the price, and a little less once your overhead recovery is in the price as well: about 16% in the worked example above.

Price it once, properly

TradeDraft prices the job the way this page does: your labour, your labourer, materials, plant and muck away as lines, your overheads recovered for the days the job takes and spread through the prices, and your markup on the bare cost, with the margin shown before you send. Free for 30 days, no card needed. After that it's £45/month or £450/year, cancel anytime. Start by 5 April 2027 and it’s £22.50/month for your first 12 months. See TradeDraft's quoting software for landscapers.

Price a job free

Want to keep this? Get our four core guides (VAT & CIS, Pricing a Job, Getting Paid, CIS for Subcontractors) as print-ready PDFs, plus a one-page job-pricing checklist — free.

We use your email to send you the toolkit, and to send updates only if you tick the box. See our Privacy Policy.

This guide is general information for UK tradespeople, current to the best of our knowledge in 2026, and is not tax, accounting or legal advice. Rates, thresholds and how they apply to you change, so confirm your position with HMRC, a qualified accountant or a solicitor before relying on it. TradeDraft accepts no liability for decisions made on the basis of this guide. Questions: hello@tradedraft.co.uk.